Tuesday, September 29, 2009

Windows

All of the windows are in except one in the master bedroom and the sliding patio door in the dining room. We are meeting with the builder and the cabinet guy today to make final decisions on the cabinets so they can be ordered tomorrow. The boring under the road for the electrical lines was also done yesterday.


Friday, September 25, 2009

Insulation



The windows have been deliver and the insulation has been put in the walls. They should be putting in the sheetrock next week.





Thursday, September 17, 2009

Pump and Fireplace Framing

Our new pump was installed on Tuesday. The framer returned and framed in the fireplace. The roofers are still working on the roof. They should finish up today. The electrician is finished and an inspection is scheduled for today.








Sunday, September 13, 2009

The Roof

The framer has finished. Hopefully the roof will be done tomorrow or Wednesday. Brad Johnson will be starting the electrical work tomorrow.

Sunday, September 6, 2009

Trusses & OSB

The framer has just a few more trusses to put up. He has more than half of the OSB on the roof. As you can see in the lower photo, he was working today in the wind and the rain. What dedication!


Saturday, September 5, 2009

The framers have been working on getting the trusses up on the house. They plan to be done by Tuesday.

Tuesday, September 1, 2009





The framer has finished putting up all of the walls. The trusses were delivered today and the trusses on the shop were put up.